A contractor has two teams of workers: team A and team B. Team A can complete a job in 12 days and team B can do the same job in 36 days. Team A starts working on the job and team B joins A after four days. Team A withdraws after two more days. For how many more days should team B work to complete the job?

  • \(24\)
  • \(16\)
  • \(22\)
  • \(18\)

Key Concepts


Arithmetic

Unitary process

Work done

Check the Answer


Answer:\(16\)

PRMO-2017, Problem 3

Pre College Mathematics

Try with Hints


At first we have to find out A's 1 days work and B's 1 days work.next find out A and B both together 1 day's work .

Can you now finish the problem ..........

Team A completes job in 12 days and Team B completes job in 36 days

1 day work of team A =\(\frac{1}{12}\)

1 day work of team B=\(\frac{1}{36}\)

1 day work of team A and team B (when they both work together \(\frac{1}{12} +\frac{1}{36}\)=\(\frac{1}{9}\)

Now according to question,
Let more number of days should team B works to complete the job be x days

\(4 \times \frac{1}{12} +2 \times \frac{1}{9} + x \times \frac{1}{36}=1\)

\(\Rightarrow x=16\)

Subscribe to Cheenta at Youtube


More Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram